Bridge Contractor Fined

Print
Updated: Fri 11:20 AM, Mar 19, 2004

Granite now has to pay $30,000 in liquidated damages for each additional day it needs to finish the new twin span Hathaway bridges.

The $81.5 million project, which began in February 2001, was supposed to have been finished by Oct. 23 last year. It was plagued by a high rate of employee turnover, two fatal accidents, and persistent rains, especially last summer.

The rainy weather helped Granite get a 92-day extension on the time limit to construct the new bridges. However, that extension ran out Jan. 24 and Granite asked for another extension. Thursday, the state Department of Transportation said no to that request.

That means a $30,000 a day penalty retroactive to January 24th. Thursday was the 54th day of the fines, which now total $1.62 million.


Weather for Panama City, Florida
80° F
Clear
Thu
91 78
Fri
87 75
Sat
87 74
Sun
89 74

Weather Cameras

8195 Front Beach Road Panama City Beach, FL 32407 Station: 850-234-7777 News: 850-230-5221 Fax: 850-233-6647
Gray Television, Inc. - Copyright © 2002-2013 - Designed by Gray Digital Media - Powered by Clickability
User Agent: CCBot/2.0 - 659386